Zurich · New build

New

Apartment building in Zurich: five storeys in shell construction

An ongoing project that I am following through to completion. More photos will follow, from shell to handover.

Five-storey shell under scaffolding, brick pallets and crane in front
Location
Zurich
Type
New build
Use
Residential
Role
Construction project manager on the client and investor side
Context
As an employee
Period
since 2026, ongoing
Further details
Details on request
Services
  • Construction project management
  • Shell inspections and quality assurance
  • Defect notices to the main contractor

Status

Shell inspection on 22.07.2026: five storeys under scaffolding, with masonry, concrete and services going in up top. The check covers what nobody will see later: insulation at the wall junction, edge protection at the roof, openings in the lift shaft and clean transitions between brick and concrete.

Defects found during the shell inspection, such as spalling on ceilings and beams or foam-filled joints, go to the main contractor as a defect notice.

I am following the project through to completion. More photos will follow.

Work on the top floor, faces made unrecognisable

Masonry and formwork up top

Wall junction with mineral wool between brick and concrete

Insulation at the wall junction

Roof edge with timber railing next to a green roof

Edge protection at the roof

View down the lift shaft with formwork

Down the lift shaft

Top floor with formwork, services and scaffolding

Services waiting for the slab

Shell under scaffolding with crane and silo, company vehicles made unrecognisable

Shell under scaffolding

Stair flight with bearing at the landing, temporary railing

Checking the stair bearing

Joint at the stair bearing filled with expanding foam

Defect: joint filled with foam

Masonry pier with chase and box for electrics

Chases in the masonry

Concrete ceiling with spalling and patch repairs

Defect: spalling on the ceiling

Wall with plumbing connections, floor not yet cleaned

Services before the screed

Downstand beam with broken edges

Defect: broken edges on the beam

Brick parapet below the window

Brick parapet below the window

Scaffolded building in October behind trees, signs and silo made unrecognisable

October: scaffolding up to the roof

Flat roof with drainage mats, substructure for solar panels and crane

On the roof: substructure for the solar system

Plasterer screeding the base coat on a wall, fair-faced concrete ceiling

Base coat: screeded wall by wall